Documents Required for Infrastructure Project
Sl.No. Documents Withdrawal Less than 10 KLD    Withdrawal between 10 to 100 KLD Withdrawal more than 100 KLD Download
Fresh (Infrastructure)
For construction activity
1 Affidavit on non-judicial stamp paper of Rs. 10/- by the applicant, confirming non/ inadequate availability of public water supply ( in case of water requirement is less than 10 KLD). OR Yes No No
2 Certificate from a government agency regarding non /partial availability of treated sewage water for construction within 10 km radius of the site in critical and over-exploited areas. No Yes Yes
3 Bharatkosh receipt for depositing Application Fee, GW abstraction/restoration charges Yes Yes Yes
4 Impact Assessment Report by Accredited Consultant in case of Dewatering is involved. No No Yes
5 Ground Water Quality Report of Existing Tube Well Yes Yes Yes
6 Scanned Copy Of Application With Signature And Seal Yes Yes Yes
7 Affidavit Yes Yes Yes
8 Ground Water Requirement Yes Yes Yes
For Drinking and Domestic use:
1 Affidavit on non judicial stamp paper of Rs. 10/- regarding non/partial availability of water from any other source in case water is required for construction in safe and semi critical areas. OR Yes No No
2 Certificate of non/partial availability of water from local government water supply agency in respect of all categories of assessment units. No Yes Yes
3 Ground water quality report of existing well from NABL accredited/govt. approved lab No Yes Yes
4 Water requirement for drinking and domestic purpose to be computed as per the National building code (NBC) 2016. (pl refer NOCAP portal, www.cgwa-noc.gov.in). Calculation of water requirement for green belt to be estimated as per the norms. (Norms: 3-5 lt./sqm) No Yes Yes
5 Completion certificate from the concerned agency for infrastructure projects. No Yes Yes
6 Installation of STP (For New Projects) in case of water requirement is more than 20 KLD No Yes Yes
7 Approval from Wetland Authority (in case of Project area falling within 500 meter of Wetland zone) Yes Yes Yes
8 Bharatkosh receipt for depositing Application Fee Yes Yes Yes
Renewal (Infrastructure)
1 Affidavit on compliance of NOC conditions for renewal cases, in case of water requirement is less than 100 KLD (pl refer NOCAP portal, www.cgwa-noc.gov.in) Yes No No
Self Compliance report (pl refer NOCAP portal, www.cgwa-noc.gov.in) No Yes Yes
2 Impact Assessment Report for OCS areas by accredited consultants (in case of water requirement is more than 100 KLD) No No Yes
Impact Assessment Report with GW modelling for OCS areas by accredited consultants (in case of water requirement is more than 500 KLD for Hard rock and 1000 KLD for Soft rock) No No Yes
Impact Assessment Report with GW modelling for Safe areas by accredited consultants (in case of water requirement is more than 500 KLD in hard rock and 2000 KLD for Soft rock) No No Yes
3 Affidavit on non-judicial stamp paper of Rs. 10/- by the applicant, confirming non/ inadequate availability of public water supply ( in case of water requirement is less than 10 KLD) OR Yes No No
4 Certificate regarding non availability of water supply from the local government water supply agency. No Yes Yes
5 Bharatkosh receipt for depositing Application Fee Yes Yes Yes
6 Approval from Wetland Authority (in case of Project area falling within 500 meter of Wetland zone) Yes Yes Yes
7 Bharatkosh receipt for depositing Application Fee, GW abstraction/restoration charges Yes Yes Yes